perfsonar-dev - Minites from 12/1/2007 Friday morning
Subject: perfsonar development work
List archive
- From: Michael Michalis <>
- To: ,
- Subject: Minites from 12/1/2007 Friday morning
- Date: Tue, 16 Jan 2007 08:27:34 +0200
Hi these are the minutes from Friday morning. Some
information about the status of the MPs is missing since I couldn’t catch
up with Loukik J. Best regards, Michalis Michael |
Loukik Kundarimoti(Going Operational-process)
---------------------------------------------
-Processes aiming at achieving high levels of customer/user satisfaction.
-Follow ITIL framework
(Brief explanation of each process).
-Service Desk Function
-Incident Management Process
-Problem Management Process
-Change Management Process
-Configuration Management Process
-Release Management Process
-Service Level Management Process
-Availability Management Process
Who will participate and lead in those processes?
Maybe some diagrams to explain this.
In Detail
Release management process
-Responsible for roll-out of new and changed software
-Strategy/release policy
-Planning
-Design
-Implementation
Also needed
-Documentation at Designining Stage
Functional and Interface Specification
Specification of Metadata config File
Specification of Property files
-Installation at Implementation Stage
Specification of Installation Actions
-Release Candidate at the end of Implemantation
This comes down finally to the:
Handover Procedure:
-------------------
-Verification of documents
-Software testing
-Installation testing
If a process has passed those tests then its included at the perfSONAR Bundle.
If not then the whole process is repeated. Many iterations possible.
Status for release management:
------------------------------
-RRD MA
-Testing almost complete
-Documentation complete by next week
-Installation verified by one member, two more due
-LS
-Testing almost complete
-Bugs found and fixed. Next iteration of testing
-Documentation complete by next week
-installation testing pending
-SQL MA
-Test scripts being prepared
-Documentation verification yet to start
-Installation testing pending
-SSH/Telnet MP
-Testing scripts at early stage
-Documenation is missing
-CLI MP
-Testing scripts at early stage
-Documentation is missing
-BWCTL MP
-Testing scripts at early stage
-Documentation is missing
-e2emon MP
-Testing yet to start
-Documentation verification pending
-Installation testing yet to start
Service Desk:
-------------
Upadate
-Yet to be setup
-Will be in charge of incident management and configuration management
-Service desk tools as CMDB being investigated
-Deploying Monitoring team and tools will be enhanced
Do other activities also have a release management? Maybe release management
should
be common for all activities.
- Minites from 12/1/2007 Friday morning, Michael Michalis, 01/16/2007
Archive powered by MHonArc 2.6.16.